Shell Waterton Plant Abatement

  • Supply, erection and dismantling of scaffold in order to remove all asbestos containing materials from 13 areas
  • Large industrial job that included asbestos removal and scaffolding
  • Eight months of low risk removal of 9,000 cubic feet of asbestos
  • Final contract value in excess of $3 million
  • Total man hours in excess of 42,000.

Project Owner:
Shell Canada Energy
Prime Contractor:
Tervita Environmental Services
Products and Services:
• Scaffolding
• Asbestos removal
Completed:
December 2012